2023-24 | CONSUMER GRIEVANCES REDRESSAL FORUM Bhuj JUDGEMENT | ||||||
SR. NO. | BHUJ FORUM REGISTRATION NUMBER | APPLICANT NAME | APPLICANT
VILLAGE- CITY |
RELATED CIRCLE OFFICE | CATEGORY CODE | DOWNLOAD | GRIEVANCE |
1 | PG04/003/2022-23 | Smt Jyotsnaben Bhojabhai Dabhi | Anjar | Anjar | 4A | Jyotsna ben dabhi.pdf | Pole related |
2 | PG04/005/2022-23 | Jasubha Velubha Sarvaiya | Vinagaber | Bhuj | 1H | Jasubha Velubha.pdf | Wongly PDC done AG connection |
3 | PG01/002/2023-24 | Deepaben S.Virwani | Gandhidham | Anjar | 4C | Deepaben virwani.pdf | Removing of Pole and TC centre in frunt of hous |
4 | PG01/001/2023-24 | Smt KrishanBen JobanPutra | Bhuj | Bhuj | 6C | Krishna ben jobanputra.pdf | Closed house wrong fualy bill issue |
5 | PG04/004/2022-23 | Jaybharat Steel Corporation | Dhamrka | Anjar | 3D | Jaybharat steel judgement.pdf | wrongly calucalated Demand charge in Open Access consumer |
6 | PG01/004/2023-24 | Pabu Maheshwari | Anjar | Anjar | 6B | CGRF judgement palu maheshwari.pdf | wrongly debited unit as per lab report |
7 | PG02/001/2023-24 | Haritage Board | Bhimasar | Anjar | 6B | CGRF judgement haritage board.pdf | Fualty meter refund related |
8 | PG02/003/2023-24 | Popat HareshKumar Nanalal | Bhachau | Anjar | 2A | Popat thacker Haresh .pdf | Pending new Lighting connection |
9 | PG02/002/2023-24 | Evert dat Herbal Beuty care | Samkhiyali | Anjar | 4A | Every day .pdf | Power supply interption releted |
10 | PG02/005/2023-24 | Gautam V.Bhatt | Bhuj | Bhuj | 2F | CGRF judgement Gautam V.Bhatt.pdf | Refund of Duplicate Estimate paid |
11 | PG02/004/2023-24 | Kanabhai Lakhubhai Chavda | Samkhiyali | Anjar | 2A | Kanabhai Lakhubhai.pdf | Not installed Meter of residence connection |
12 | PG03/001/2023-24 | Jadeja Diptiba Hardevsing | Antar Jad | Anjar | 6A | Jadeja dipti ba.pdf | Regarding mistake in July /August 2023 Bill |
13 | PG03/002/2023-24 | Jadeja Narendra sinh Ladhubha | Adipur | Anjar | 6B | CGRF judgement Narendra sinh ladhubha.pdf | fast meter bill for the month of May/June 2023 |
14 | PG03/003/2023-24 | Rohini Pruviraj Kotak | Madhapar | Bhuj | 2D | CGRF judgement Rohini prutiviraj.pdf | Pole shiftin wrong FQ received |
15 | PG03/004/2023-24 | Ram vastabhai Odedara | Madhapar | Bhuj | 6D | ramvasta CGRF.pdf | Security Deposit refund not received |
16 | PG03/005/2023-24 | Abbas Hasam Tarwani | Bhuj | Bhuj | 6A | Abbas hasam Tarrwani.pdf | Regarding Debit amount as per lab report |
17 | PG03/007/2023-24 | Kanabhai valabhai Dangar | Dhaneti | Bhuj | 2D | Kanabhai valabhai Dangar.pdf | Regarding debit amount after two years from date of connection |
18 | PG03/006/2023-24 | A.G.S.Ind Ltd | Satapar | Anjar | 6B | CGRF Judgement AGS Ind.pdf | Regarding refund of Average Bill given in Faulty meter |
19 | PG03/008/2023-24 | Sal Steel Ltd | Bharapar | Anjar | 3D | CGRF judgement sal steel.pdf[1] | Regarding wrong MD bill of the month of July 2023 |
21 | PG04/001/2023-24 | Jentilal Laladhar Soni | Mandvi | Bhuj | 4A | CGRF judgement Jentilal L Soni.pdf | Claim agains damage due to volatage factuation |
22 | PG04/004/2023-24 | Chetan Kanji Nishoar | Bhachau | Anjar | 6A | CGRF judgemetn chetan kanji Nishar.pdf | Due late PD wrong arreares arise |
23 | PG04/003/2023-24 | Zala Ranjet sinh Chatrasinh | Bhuj | Bhuj | 6A | CGRF Judgement Zala Ranjit Sinh .pdf | After instlling solar Bill excess |
24 | PG04/002/2023-24 | Varvo Panels LLP | Choparwa | Anjar | 3C | Varvo panel LL P.pdf | refund of estimae charge wrongly collected |
25 | PG04/006/2023-24 | Jequer & company Pvt Ltd | Bhachau | Anjar | 6B | Jequar & co.pdf | fast meter bill of Month July August 2023 |