Performa SoP 003 B: APPENDIX-B (already in the SoP regulation)
REGISTER FOR COMPILING THE COMPLAINTS CLASSIFICATIONWISE
Name of Area / Circle Classification Pending complaints of previous Qtr Complaints received during the Qtr Total Complaints No. of Complaints redressed during the Qtr Balance Complaints to be redressed
(5) – (10)
In stipulated time Beyond stipulated time Total (6) to (9)
Within 50% of stipulated time. Within stipulated time. Up to double the stipulated time More than double the stipulated time
1 2 3 4.00 5 6.00 7.00 8.00 9.00 10 11
PGVCL A(i) Loose connections from pole 166 45073 45239 23866 21142 110 4 45122 117
A(ii) Interruption due to line breakdown 181 16587 16768 8878 7656 125 7 16666 102
A(iii) Interruption due to failure of transformer 174 6733 6907 3756 3063 20 1 6840 67
B(i) Ordinary case, which requires no augmentation. 108 1336 1444 772 610 22 0 1404 40
B(ii) Where augmentation is required. 187 1058 1245 512 674 15 0 1201 44
C(i) Stopped/Defective Meters 114 10878 10992 6017 4891 31 10 10949 43
C(ii) Billing on average basis for more than two bills 131 3950 4081 1815 2200 6 0 4021 60
D(i) Loose Wires 52 4955 5007 2457 2538 7 1 5003 4
D(ii) Inadequate ground clearance 168 1361 1529 712 760 8 0 1480 49
E(i) For current bills where no additional information is required 428 3070 3498 2032 1412 10 0 3454 44
E(ii) Where additional information relating to correctness of reading etc. is required 110 2792 2902 1547 1314 12 0 2873 29
F(i) Where extension of mains is not required 135 2084 2219 1235 933 8 0 2176 43
F(ii) Where extension of mains is required 151 1166 1317 598 636 31 0 1265 52
F(iii) Modification in connected load 144 2136 2280 1198 985 5 0 2188 92
F(iv) Name change/reconnection 211 10997 11208 4881 6174 36 4 11095 113
G Refund of amount due in regard to temporary connection 67 943 1010 506 442 22 15 985 25
H Others 218 5196 5414 2373 2921 17 16 5327 87
2745 120315 123060 63155 58351 485 58 122049 1011