Performa SoP 003 B: APPENDIX-B (already in the SoP regulation)
REGISTER FOR COMPILING THE COMPLAINTS CLASSIFICATIONWISE
Name of Area / Circle Classification Pending complaints of previous Qtr Complaints received during the Qtr Total Complaints No. of Complaints redressed during the Qtr Balance Complaints to be redressed
(5) – (10)
In stipulated time Beyond stipulated time Total (6) to (9)
Within 50% of stipulated time. Within stipulated time. Up to double the stipulated time More than double the stipulated time
1 2   3 4 5 6 7 8 9 10 11
PGVCL A(i) Loose connections from pole 4 62254 62258 37325 24933 0 0 62258 0
A(ii) Interruption due to line breakdown 0 23720 23720 10494 13226 0 0 23720 0
A(iii) Interruption due to failure of transformer 2 7071 7073 3736 3337 0 0 7073 0
B(i) Ordinary case, which requires no augmentation. 2 796 798 368 430 0 0 798 0
B(ii) Where augmentation is required. 4 884 888 379 509 0 0 888 0
C(i) Stopped/Defective Meters 59 12519 12578 4992 7517 0 0 12509 69
C(ii) Billing on average basis for more than two bills 53 3556 3609 1739 1796 0 0 3535 74
D(i) Loose Wires 16 6615 6631 3446 3147 0 0 6593 38
D(ii) Inadequate ground clearance 2 1002 1004 399 605 0 0 1004 0
E(i) For current bills where no additional information is required 21 3972 3993 2531 1431 0 0 3962 31
E(ii) Where additional information relating to correctness of reading etc. is required 31 4143 4174 1561 2579 0 0 4140 34
F(i) Where extension of mains is not required 0 1893 1893 1109 784 0 0 1893 0
F(ii) Where extension of mains is required 0 1406 1406 831 575 0 0 1406 0
F(iii) Modification in connected load 3 2430 2433 1175 1234 0 0 2409 24
F(iv) Name change/reconnection 65 6315 6380 3185 3117 0 0 6302 78
G Refund of amount due in regard to temporary connection 64 842 906 340 484 0 0 824 82
H Others 65 4785 4850 2465 2301 0 0 4766 84