Performa SoP 003 B: APPENDIX-B (already in the SoP regulation)
REGISTER FOR COMPILING THE COMPLAINTS CLASSIFICATIONWISE
Name of Area / Circle Classification Pending complaints of previous Qtr Complaints received during the Qtr Total Complaints No. of Complaints redressed during the Qtr Balance Complaints to be redressed
(5)-(10)
In stipulated time Beyond stipulated time Total (6) to (9)
Within 50% of stipulated time. Within stipulated time. Up to double the stipulated time More than double the stipulated time
1 2   3 4 5 6 7 8 9 10 11  
PGVCL A(i) Loose connections from pole 26 82148 80824 52339 29273 462 71 82145 29
A(ii) Interruption due to line breakdown 16 59522 58216 33992 25028 424 77 59521 17
A(iii) Interruption due to failure of transformer 31 21137 20438 11402 8926 782 27 21137 31
B(i) Ordinary case, which requires no augmentation. 17 2480 2431 1160 1286 34 0 2480 17
B(ii) Where augmentation is required. 36 1375 1365 581 749 38 7 1375 36
C(i) Stopped/Defective Meters 23 16320 15717 9085 7150 74 9 16318 25
C(ii) Billing on average basis for more than two bills 20 5776 5405 3231 2446 94 7 5778 18
D(i) Loose Wires 28 11066 10601 6499 4451 107 11 11068 26
D(ii) Inadequate ground clearance 1 2225 2226 1208 982 29 6 2225 1
E(i) For current bills where no additional information is required 4 4803 4349 3040 1701 48 14 4803 4
E(ii) Where additional information relating to correctness of reading etc. is required 9 3169 2754 1857 1289 17 5 3168 10
F(i) Where extension of mains is not required 2 2132 2058 1169 928 32 3 2132 2
F(ii) Where extension of mains is required 1 1263 1239 685 547 25 6 1263 1
F(iii) Modification in connected load 12 4454 4208 2441 1933 73 7 4454 12
F(iv) Name change/reconnection 15 9010 8790 5336 3623 46 6 9011 14
G Refund of amount due in regard to temporary connection 10 1886 1873 877 983 27 0 1887 9
H Others 26 25833 23799 15763 9935 131 8 25837 7
277 254599 246293 150665 101230 2443 264 254602 259