Performa SoP 003 B: APPENDIX-B (already in the SoP regulation)
REGISTER FOR COMPILING THE COMPLAINTS CLASSIFICATIONWISE FOR THE YEAR 2013-14
Qtr Classification Pending complaints of previous Qtr Complaints received during the Qtr Total Complaints No. of Complaints redressed during the Qtr Balance Complaints to be redressed
(5) – (10)
In stipulated time Beyond stipulated time Total (6) to (9)
Within 50% of stipulated time. Within stipulated time. Up to double the stipulated time More than double the stipulated time
1 2 3 4 5 6 7 8 9 10 11
1 A(i) Loose connections from pole 63 54651 54714 28039 25557 907 172 54675 39
A(ii) Interruption due to line breakdown 3 18488 18491 9101 9214 141 26 18482 9
A(iii) Interruption due to failure of transformer 24 8785 8809 4052 4648 72 8 8780 29
B(i) Ordinary case, which requires no augmentation. 0 1804 1804 894 889 19 0 1802 2
B(ii) Where augmentation is required. 18 1121 1139 508 606 19 0 1133 6
C(i) Stopped/Defective Meters 20 11169 11189 5291 5751 101 10 11153 36
C(ii) Billing on average basis for more than two bills 19 4333 4352 1885 2406 42 5 4338 14
D(i) Loose Wires 1 5255 5256 2557 2594 59 3 5213 43
D(ii) Inadequate ground clearance 7 1464 1471 717 735 19 0 1471 0
E(i) For current bills where no additional information is required 7 3538 3545 2108 1412 12 0 3532 13
E(ii) Where additional information relating to correctness of reading etc. is required 7 2784 2791 1370 1366 40 6 2782 9
F(i) Where extension of mains is not required 0 2662 2662 1392 1218 51 0 2661 1
F(ii) Where extension of mains is required 0 1581 1581 674 878 28 0 1580 1
F(iii) Modification in connected load 1 2579 2580 1308 1221 46 0 2575 5
F(iv) Name change/reconnection 2 8984 8986 4105 4626 203 43 8977 9
G Refund of amount due in regard to temporary connection 17 1455 1472 694 694 29 0 1417 55
H Others 12 4147 4159 1625 2346 131 18 4120 39
2 A(i) Loose connections from pole 39 73237 73276 31808 40752 327 110 72997 279
A(ii) Interruption due to line breakdown 9 20473 20482 7936 11858 235 136 20165 317
A(iii) Interruption due to failure of transformer 29 10804 10833 4708 5767 58 73 10606 227
B(i) Ordinary case, which requires no augmentation. 2 1994 1996 823 974 65 27 1889 107
B(ii) Where augmentation is required. 6 1370 1376 453 633 68 34 1188 188
C(i) Stopped/Defective Meters 36 12473 12509 5668 6509 143 39 12359 150
C(ii) Billing on average basis for more than two bills 14 4346 4360 1703 2424 74 8 4209 151
D(i) Loose Wires 43 7234 7277 3098 3963 93 43 7197 80
D(ii) Inadequate ground clearance 0 1840 1840 734.8 866 62 15 1677.8 162.2
E(i) For current bills where no additional information is required 13 3984 3997 2181.85 1289 62 26 3558.85 438.15
E(ii) Where additional information relating to correctness of reading etc. is required 9 3156 3165 1215.3 1763 32 32 3042.3 122.7
F(i) Where extension of mains is not required 1 2952 2953 1456.45 1287 56 2 2801.45 151.55
F(ii) Where extension of mains is required 1 1419 1420 520.3 704 34 10 1268.3 151.7
F(iii) Modification in connected load 5 2846 2851 1308.9 1309 33 16 2666.9 184.1
F(iv) Name change/reconnection 9 12271 12280 5119.25 6834 66 8 12027.25 252.75
G Refund of amount due in regard to temporary connection 55 1495 1550 663.15 735 41 17 1456.15 93.85
H Others 39 5479 5518 2444.75 2794 35 14 5287.75 230.25
3 A(i) Loose connections from pole 279 41846 42125 24369 2794 233 4 27400 14725
A(ii) Interruption due to line breakdown 317 16182 16499 9353 6859 101 5 16318 181
A(iii) Interruption due to failure of transformer 227 6508 6735 3061 3462 34 4 6561 174
B(i) Ordinary case, which requires no augmentation. 107 1557 1664 913 596 47 0 1556 108
B(ii) Where augmentation is required. 188 1240 1428 555 665 21 0 1241 187
C(i) Stopped/Defective Meters 150 10506 10656 5670 4672 150 50 10542 114
C(ii) Billing on average basis for more than two bills 151 3358 3509 1525 1797 51 5 3378 131
D(i) Loose Wires 80 4465 4545 2261 2181 47 4 4493 52
D(ii) Inadequate ground clearance 162 1088 1250 557 506 19 0 1082 168
E(i) For current bills where no additional information is required 438 2792 3230 1692 1112 17 1 2822 408
E(ii) Where additional information relating to correctness of reading etc. is required 123 2527 2650 1391 1091 48 2 2532 118
F(i) Where extension of mains is not required 152 2135 2287 1231 905 16 0 2152 135
F(ii) Where extension of mains is required 152 1000 1152 450 542 9 0 1001 151
F(iii) Modification in connected load 184 2133 2317 1202.9985 936 34 0 2172.9985 144.0015
F(iv) Name change/reconnection 253 9504 9757 4954 4316 275 1 9546 211
G Refund of amount due in regard to temporary connection 94 964 1058 493 473 25 0 991 67
H Others 230 3599 3829 1888 1621 101 1 3611 218
4 A(i) Loose connections from pole 166 45073 45239 23866 21142 110 4 45122 117
A(ii) Interruption due to line breakdown 181 16587 16768 8878 7656 125 7 16666 102
A(iii) Interruption due to failure of transformer 174 6733 6907 3756 3063 20 1 6840 67
B(i) Ordinary case, which requires no augmentation. 108 1336 1444 772 610 22 0 1404 40
B(ii) Where augmentation is required. 187 1058 1245 512 674 15 0 1201 44
C(i) Stopped/Defective Meters 114 10878 10992 6017 4891 31 10 10949 43
C(ii) Billing on average basis for more than two bills 131 3950 4081 1815 2200 6 0 4021 60
D(i) Loose Wires 52 4955 5007 2457 2538 7 1 5003 4
D(ii) Inadequate ground clearance 168 1361 1529 712 760 8 0 1480 49
E(i) For current bills where no additional information is required 428 3070 3498 2032 1412 10 0 3454 44
E(ii) Where additional information relating to correctness of reading etc. is required 110 2792 2902 1547 1314 12 0 2873 29
F(i) Where extension of mains is not required 135 2084 2219 1235 933 8 0 2176 43
F(ii) Where extension of mains is required 151 1166 1317 598 636 31 0 1265 52
F(iii) Modification in connected load 144 2136 2280 1198 985 5 0 2188 92
F(iv) Name change/reconnection 211 10997 11208 4881 6174 36 4 11095 113
G Refund of amount due in regard to temporary connection 67 943 1010 506 442 22 15 985 25
H Others 218 5196 5414 2373 2921 17 16 5327 87
Total 6543 533892 540435 262883 249501 5116 1036 518536 21899
Qtr Classification Pending complaints of previous Year Complaints received during the Year Total Complaints No. of Complaints redressed during the Qtr Balance Complaints to be redressed
(5) – (10)
In stipulated time Beyond stipulated time Total (6) to (9)
Within 50% of stipulated time. Within stipulated time. Up to double the stipulated time More than double the stipulated time
   
  A(i) Loose connections from pole 547 214807 215354 108082 90245 1577 290 200194 15160
  A(ii) Interruption due to line breakdown 510 71730 72240 35268 35587 602 174 71631 609
  A(iii) Interruption due to failure of transformer 454 32830 33284 15577 16940 184 86 32787 497
  B(i) Ordinary case, which requires no augmentation. 217 6691 6908 3402 3069 153 27 6651 257
  B(ii) Where augmentation is required. 399 4789 5188 2028 2578 123 34 4763 425
  C(i) Stopped/Defective Meters 320 45026 45346 22646 21823 425 109 45003 343
  C(ii) Billing on average basis for more than two bills 315 15987 16302 6928 8827 173 18 15946 356
  D(i) Loose Wires 176 21909 22085 10373 11276 206 51 21906 179
  D(ii) Inadequate ground clearance 337 5753 6090 2721 2867 108 15 5711 379
  E(i) For current bills where no additional information is required 886 13384 14270 8014 5225 101 27 13367 903
  E(ii) Where additional information relating to correctness of reading etc. is required 249 11259 11508 5523 5534 132 40 11229 279
  F(i) Where extension of mains is not required 288 9833 10121 5314 4343 131 2 9790 331
  F(ii) Where extension of mains is required 304 5166 5470 2242 2760 102 10 5114 356
  F(iii) Modification in connected load 334 9694 10028 5018 4451 118 16 9603 425
  F(iv) Name change/reconnection 475 41756 42231 19059 21950 580 56 41645 586
  G Refund of amount due in regard to temporary connection 233 4857 5090 2356 2344 117 32 4849 241
  H Others 499 18421 18920 8331 9682 284 49 18346 574
    Total  6543 533892 540435 262883 249501 5116 1036 518536 21899